Transmission and Distribution Transformers Compared

The grid has three stages and transformers sit at each boundary. Knowing which stage you are buying for sets the voltage class, the price and the lead time.

TransmissionDistribution
Voltage69 kV to 765 kV4.16 kV to 34.5 kV
JobMove bulk power long distancesDeliver to the customer
Transformer typeLarge power transformersDistribution transformers, pad and pole
RatingTens to hundreds of MVA5 kVA to 2500 kVA
Lead time nowThree to five yearsForty to sixty weeks, or days from stock
Who buysUtilities and transmission operatorsUtilities, developers, contractors
CoolingForced oil, forced air, radiator banksUsually self cooled, no fans
ImpedanceTypically 8 to 15 percentTypically 2 to 6 percent
Installed onFoundations in a fenced substationA concrete pad, or a pole
Price per kVALower, but the unit runs to millionsHigher, but the unit is affordable

Which you actually need

Anything feeding a building is distribution. The three to five year lead times that make the news are on the transmission side, on large power transformers. Distribution lead times are bad but they are a different order of problem, and stock exists.

The three to five year lead times reported in the press are transmission class equipment, and they are genuine. Distribution transformers are also constrained but the problem is different in kind, measured in months not years, and stock genuinely exists if you are willing to pay for it.

If someone quotes you a multi year wait for a 300 kVA pad-mount, they are either quoting the wrong product or they have no stock relationship. Neither is your problem to accept.